MVI Entry & Exit Criteria |
|
Entry Criteria Exit Criteria Back to The MVI Process
The following entry criteria must be
met before the testing can commence:
IOT, if applicable, has been completed and test reports are available.
MVI test plans have been agreed by all involved
parties and are available.
A
schedule for testing is agreed by all parties.
Network parameters and configurations are
agreed, and the required resources are available.
The following exit criteria must be
met before testing is deemed to be complete:
All test cases defined in the test plan
have been performed, unless all parties agree to exclude them.
A test report has been prepared and
agreed by all parties.
An action plan has been prepared and agreed by all parties in order to cover any outstanding items.
An official wrap-up meeting has been held.